For your information, the following is a list of “Key” activities that will be occurring around the site over the next couple of weeks.

1. F-East

  • Structural steel erection complete
  • Top out celebration October 4th, 2021
  • Fireproofing of steel columns on-going
  • CMU block installation ongoing
  • MEP rough installation ongoing
  • GFRC installation to start mid-October
  • Roofing to start mid-October
  • Water and sewer connections to start the week of October 18. Expect some road closures on NE 8 street, between 1st ave and 2nd

 

2. Private Improvement Areas

  • 1st Ave: The slab was poured. We continue installing utilities and we will install Landscape on September. The sidewalk is temporarily closed.
  • 2nd Ave: Part of the Landscape was installed. We continue installing pavers.
  • Half of 7ST street: Part of the Landscape was installed. We continue installing pavers. The sidewalk is temporarily closed.
  • LUMA Drop Off: Part of the slab was poured and some bollards were installed.

 

3. Block H and Bezel

  • STO Crotique Install on Art Wall Framing on West Elevation – In progress
  • Interior Garage Striping – Complete
  • Garage Louver Installation – Complete
  • Finalizing details on Lvl 13 Roof – Complete
  • Elevators 6 & 7 – Final Inspections. Elev. 8 & 9 – Final Adjustments
  • North Elevation Exterior Lights Installed – Installation Complete Adjustment On-going