For your information, the following is a list of “Key” activities that will be occurring around the site over the next couple of weeks.
- Paramount:
- Partial Lane Closure on NE 8th St. corner with 1st Ave.
- Duration:08/01/19 – 09/20/19
- Time: from 7:30 AM to 6:30 PM
- Full Street Closure: NE 8th Street between NE 1st and 2nd Ave.
- Duration: 09/05/19– 09/07/19
- Time: from 8:00 AM to 4:00 PM
- Partial Lane closure; two lanes (West Side) on 1st Ave. between NE 8th and NE 10th Street for the placement of a crane.
- Duration:09/09/19– 09/13/19
- Time:8:00 AM to 4:00 PM
- Full Closure – NE 8th Street between NE 1 Ave and NE 2 Ave
- Duration: 09/14/19 – 09/19/19
- Time:8:00 AM to 4:00 PM
- Interior finishes continue
- Façade panel installation continues
- Amenity deck continues
- Partial Lane Closure on NE 8th St. corner with 1st Ave.
- MWC Luma
- Site
- Reinstalling vision screen
- Tower
- Forming and pouring verticals – daytime
- Pulling sheet piles – daytime
- Garage
- Excavating foundations
- Chipping piles
- FRP foundations
- FRP verticals
- Site
- Street Closures
- Starting Sunday 9/15 to Wednesday 9/18 from 9PM to 6AM
- Milling N Miami Ave from RR Tracks to NE 9th ST
- Milling NE 9th ST from N Miami Ave to NE 1st Ave
- Milling NE 1st Ave from RR Tracks to NE 6th ST
- Final Lift on NE 8th ST from NE 1st Ave to NE 2nd Ave
- Final Lift of NE 10th ST from NE 1st Ave to NE 2nd Ave
- 9/16 Partial Closures starting at 9:00 PM – 6:00 A
- Final lift of NE 1st Ave from NE 6th ST to NE 10th ST
- 9/17 Partial Closures starting at 9:00 PM – 6:00 AM
- Milling of NE 2nd Ave from NE 10th ST to RR Tracks
- Final Lift of N Miami Ave from RR Tracks to NE 9th ST
- Final Lift of NE 9th ST from NE 1st Ave to N Miami Ave
- 9/18 Partial Closures starting at 9:00 PM – 6:00 AM
- Final Lift of NE 2nd Ave
- Starting Sunday 9/15 to Wednesday 9/18 from 9PM to 6AM