For your information, the following is a list of “Key” activities that will be occurring around the site over the next couple of weeks.
1. F-East
- Structural steel erection ongoing
- Metal deck installation ongoing
- Concrete slab pours on levels 2 and 3 ongoing
- Fireproofing of steel columns started
2. Private Improvement Areas
- 1st Ave: The slab was poured. We continue installing utilities and we will install Landscape on September. The sidewalk is temporarily closed.
- 2nd Ave: Part of the Landscape was installed. We continue installing pavers.
- Half of 7ST street: Part of the Landscape was installed. We continue installing pavers. The sidewalk is temporarily closed.
- Bezel Drop Off: Part of the slab was poured and some bollards were installed.
3. Block H Garage and Retail
- STO Maleano Install for Art Wall on West Elevation Complete
- STO Crotique Install on Art Wall Framing on West Elevation – on going
- Interior Garage Striping nearing completion
- Garage Louver Installation on going
- Finalizing details on Lvl 13 Roof
- Elevators being adjusted and phone line installed
- Lvl 9 Planters on site
F-East
Private Improvement Areas
Block H