For your information, the following is a list of “Key” activities that will be occurring around the site over the next couple of weeks.

1. F-East

  • Structural steel erection ongoing
  • Metal deck installation ongoing
  • Concrete slab pours on levels 2 and 3 ongoing
  • Fireproofing of steel columns started

2. Private Improvement Areas

  • 1st Ave: The slab was poured. We continue installing utilities and we will install Landscape on September. The sidewalk is temporarily closed.
  • 2nd Ave: Part of the Landscape was installed. We continue installing pavers.
  • Half of 7ST street: Part of the Landscape was installed. We continue installing pavers. The sidewalk is temporarily closed.
  • Bezel Drop Off: Part of the slab was poured and some bollards were installed.

3. Block H Garage and Retail

  • STO Maleano Install for Art Wall on West Elevation Complete
  • STO Crotique Install on Art Wall Framing on West Elevation – on going
  • Interior Garage Striping nearing completion
  • Garage Louver Installation on going
  • Finalizing details on Lvl 13 Roof
  • Elevators being adjusted and phone line installed
  • Lvl 9 Planters on site

 

F-East

 

Private Improvement Areas

 

Block H