For your information, the following is a list of “Key” activities that will be occurring around the site over the next couple of weeks.
- Paramount:
- Full Street Closure: NE 8th Street between NE 1st and 2nd Ave.
- Duration: 10/07/19 – 10/31/19
- Time: from 8:00 AM to 4:00 PM
- Interior finishes continue
- Façade panel installation continue
- Amenity deck continues
- Single lane closure: NE 1 Ave between NE 8 and 10 Street
- Duration: 10/07/19 – 10/31/19
- Time: 08:00 AM – 05:00 PM
- Full Street Closure: NE 8th Street between NE 1st and 2nd Ave.
- Site work:
- Partial Closure: NE 8 Street between NE 1 and 2 Ave.
- Duration: 10/21/19 – 10/22/19
- Times: 8:00 AM – 5:00PM
- Partial Closure: NE 1 Ave between NE 8 and 10 street
- Duration: 10/22/19 -10/23/19
- Times: 8:00 AM – 5:00 PM
- Partial Closure: NE 10 street between NE 1 and 2 Ave.
- Duration: 10/23/19 -10/24/19
- Times: 8:00 AM – 5:00 PM
- Partial Closure: NE 2 Ave between NE 1 Ave and Biscayne Blvd.
- Duration: 10/24/19 -10/25/19
- Times: 8:00 AM – 5:00 PM
- Partial Closure: NE 8 Street between NE 1 and 2 Ave.
- MWC Luma
- Tower
- Forming and pouring verticals – daytime
- Forming Slabs – daytime 46 NE 6 Street Miami, FL 33132
- Pouring Slabs
- Start Time: 03:00 AM
- Dates: 10/22/19 and 10/30/19
- Garage
- FRP Verticals
- Backfilling and hauling off excess dirt
- Demobilizing dewatering equipment
- Shoring material delivery and set up daily
- Pouring Garage Slabs –
- Start Time: 03:00 AM
- Date: 10/30/19
- Tower