For your information, the following is a list of “Key” activities that will be occurring around the site over the next couple of weeks.
1. F-East
- Structural steel erection complete
- Top out celebration October 4th, 2021
- Fireproofing of steel columns on-going
- CMU block installation ongoing
- MEP rough installation ongoing
- GFRC installation to start mid-October
- Roofing to start mid-October
- Water and sewer connections to start the week of October 18. Expect some road closures on NE 8 street, between 1st ave and 2nd
2. Private Improvement Areas
- 1st Ave: The slab was poured. We continue installing utilities and we will install Landscape on September. The sidewalk is temporarily closed.
- 2nd Ave: Part of the Landscape was installed. We continue installing pavers.
- Half of 7ST street: Part of the Landscape was installed. We continue installing pavers. The sidewalk is temporarily closed.
- LUMA Drop Off: Part of the slab was poured and some bollards were installed.
3. Block H and Bezel
- STO Crotique Install on Art Wall Framing on West Elevation – In progress
- Interior Garage Striping – Complete
- Garage Louver Installation – Complete
- Finalizing details on Lvl 13 Roof – Complete
- Elevators 6 & 7 – Final Inspections. Elev. 8 & 9 – Final Adjustments
- North Elevation Exterior Lights Installed – Installation Complete Adjustment On-going