For your information, the following is a list of “Key” activities that will be occurring around the site over the next couple of weeks.

  1. Paramount:
    • Full Street Closure: NE 8th Street between NE 1st and 2nd Ave.
      • Duration: 11/11/19 – 11/18/19
      • Time: from 8:00 AM to 4:00 PM
    • Interior finishes continue
    • Façade panel installation continue
    • Amenity deck continues
    • Two lane closure: NE 1 Ave between NE 8 and 10 Street
      • Duration: 10/28/19 – 11/05/19
      • Time: 08:00 AM – 03:00 PM
    • One lane closure: NE 1 Ave between NE 8 and 10 Street
      • Duration: 11/05/19 – 11/26/19
      • Time: 08:00 AM – 04:00 PM
  2. Site work:
    • Partial Closure: NE 8 Street between NE 1 and 2 Ave.
      • Duration: 10/21/19 – 11/08/19
      • Times: 8:00 AM – 3:00PM
    • Partial Closure: NE 1 Ave between NE 8 and 10 street
      • Duration: 10/22/19 -11/08/19
      • Times: 8:00 AM – 3:00 PM
    • Partial Closure: NE 10 street between NE 1 and 2 Ave.
      • Duration: 10/23/19 -11/08/19
      • Times: 8:00 AM – 3:00 PM
    • Partial Closure: NE 2 Ave between NE 1 Ave and Biscayne Blvd.
      • Duration: 10/24/19 -11/08/19
      • Times: 8:00 AM – 3:00 PM
  3. MWC Luma
    • Tower
      • Forming and pouring verticals – daytime
      • Forming Slabs – daytime
      • Pouring Slabs
      • FRP Verticals at Garage
      • Concrete Pours schedule for the following week
        • Date: 11/06/19 – Start Time: 02:00 AM to 7 AM
        • Date: 11/09/19 thru 11/15/19 – Start Time: 04:00 AM