Construction Update: Week of Nov 2, 2021

November 3, 2021

For your information, the following is a list of “Key” activities that will be occurring around the site over the next couple of weeks.

1. F-East

  • Fireproofing of steel columns on-going
  • CMU block installation ongoing
  • MEP rough installation ongoing
  • GFRC installation to start mid-November
  • Glass installation to start mid- November
  • Roofing to start mid-November
  • Water and sewer connections to start week of November 8. Expect some road closures on NE 8 street, between 1st ave and 2nd

2. Private Improvement Areas

  • 1st Ave: Landscape was installed. In November, we will install pavers. The sidewalk is temporarily closed.
  • 2nd Ave: Landscape, Pavers and lighting were installed. In November, we will install polymeric sand. The sidewalk is temporarily closed.
  • Half of 7ST street: Landscape, Pavers and lighting were installed. In November, we will install polymeric sand. The sidewalk is temporarily closed.
  • Bezel Drop Off: Landscape and Pavers were installed. In November, we will install polymeric sand. The area is temporarily closed.

3. Block H Garage and Retail

  • STO Crotique Install on Art Wall Framing on West Elevation – COMPLETE
  • Garage – Lvls 2-11 – Punching Out for Final Completion
  • Elevators 6 & 7 / Elev. 8 & 9 – Final Inspections
  • North Elevation Exterior Lights Installed – Installation Complete Adjustment On-going
  • East Portal Base – Lights on Going

4. Bezel Apartments – Now Leasing 

 