For your information, the following is a list of “Key” activities that will be occurring around the site over the next couple of weeks.
- Paramount:
- Partial Lane Closure on NE 10th St. between NE 1st Ave and NE 2nd Ave.:
- Duration: 05/01/19 – 05/31/19
- Time: from 7:30 AM to 6:30 PM
- Partial Lane closure; two most eastern lanes on 1st Ave. between NE 8th and NE 10th Street.
- Duration: 05/01/19 – 05/31/19
- Time: 24 Hours
- Building Enclosure at Podium continues
- Interior finishes continue
- Amenity deck continues
- Partial Lane Closure on NE 10th St. between NE 1st Ave and NE 2nd Ave.:
- Block D East:
- Elevators testing is ongoing and nearing completion.
- Installation of the metal fins started on the north elevation.
- Installation of the steel supporting members for the louvers continues.
- Off-site utilities installation along 2nd Avenue continues.
- Site Work:
- 2 Lane closure on N Miami Ave. between 8th St. and R/R tracks.
- Excavation and installation of drainage
- Time: 8AM to 4PM
- Duration 05/03/19 – 05/11/19
- Full Closure of NE 8th St. Between NE 1st and NE 2nd Ave due to Gas line installation.
- Time: 8AM to 4PM
- Duration 05/15/2019 to 05/17/2019
- Partial Lane Closure (2 Traffic Lanes) on NE 2nd Ave between NE 9th ST and NE 10th ST
- Excavation of landscape area behind curb
- Time: 8AM to 4PM
- Duration 05/08/2019 to 05/15/2019
- 2 Lane closure on N Miami Ave. between 8th St. and R/R tracks.
- MWC Luma
- Demolition of Unforeseen Concrete Foundations
- Grading Site to 9.00NGVD
- Haul Off of Site Soil and Demolition Soil
- Test Pile and Production Program (will extend to after 5 PM)
- Drilling of temporary and Permanent Drainage Wells
NOTE: All Concrete pours anticipated to start at 1am.