For your information, the following is a list of “Key” activities that will be occurring around the site over the next couple of weeks.

  1. Paramount:
    • Partial Lane Closure on NE 10th St. between NE 1st Ave and NE 2nd Ave.:
      • Duration: 05/01/19 – 05/31/19
      • Time: from 7:30 AM to 6:30 PM
    • Partial Lane closure; two most eastern lanes on 1st Ave. between NE 8th and NE 10th Street.
      • Duration: 05/01/19 – 05/31/19
      • Time: 24 Hours
    • Building Enclosure at Podium continues
    • Interior finishes continue
    • Amenity deck continues
  2. Block D East:
    • Elevators testing is ongoing and nearing completion.
    • Installation of the metal fins started on the north elevation.
    • Installation of the steel supporting members for the louvers continues.
    • Off-site utilities installation along 2nd Avenue continues.
  3. Site Work:
    • 2 Lane closure on N Miami Ave. between 8th St. and R/R tracks.
      • Excavation and installation of drainage
      • Time:  8AM to 4PM
      • Duration 05/03/19 – 05/11/19
    • Full Closure of NE 8th St. Between NE 1st and NE 2nd Ave due to Gas line installation.
      • Time: 8AM to 4PM
      • Duration  05/15/2019 to 05/17/2019
    • Partial Lane Closure (2 Traffic Lanes) on NE 2nd Ave between NE 9th ST and NE 10th ST
      • Excavation of landscape area behind curb
      • Time: 8AM to 4PM
      • Duration 05/08/2019 to 05/15/2019
  4. MWC Luma
    • Demolition of Unforeseen Concrete Foundations
    • Grading Site to 9.00NGVD
    • Haul Off of Site Soil and Demolition Soil
    • Test Pile and Production Program (will extend to after 5 PM)
    • Drilling of temporary and Permanent Drainage Wells

NOTE: All Concrete pours anticipated to start at 1am.