For your information, the following is a list of “Key” activities that will be occurring around the site over the next couple of weeks.

  1. Paramount:
    • Villa area Amenity deck construction continues
    • NE 1 Ave between NE 8th and NE 9th Sidewalk closure – paver replacement at Garage entry for Paramount.
      • Dates: 03/02/20 – 03/15/20
      • Times: 08:00 AM – 04:00 PM
  2. MWC Luma
    • Tower / Garage
      • Forming and pouring verticals – daytime
      • Concrete Slab Pours start at 04:00 AM
      • FRP Verticals at Garage
      • MEP Installation Underground
      • Block installation on L1 of both the garage and the tower
      • Window Installation, MEP rough in and framing continues