For your information, the following is a list of “Key” activities that will be occurring around the site over the next couple of weeks.
- Paramount:
- Partial Lane Closure on NE 10th St. between NE 1st Ave and NE 2nd Ave.:
- Duration: 03/08/19 – 03/22/19
- Time: from 7:30 AM to 6:30 PM
- Partial Lane Closure on NE 10th St. between NE 1st Ave and NE 2nd Ave.:
- Block D East:
- Elevators Installation is ongoing.
- Installation Façade Metal panels on the east elevation is ongoing.
- Installation of the steel supporting members for the louvers continues.
- Off-site utilities installation along 2nd Avenue continues.
- Site Work:
- Partial Closure on NE 8th St. Between NE 1st and NE 2nd Ave due to Gas line installation.
- Time: 7AM to 4PM
- Duration 02/25/2019 to 03/22/2019
- Partial Closure on NE 1st Ave. Between NE 1st from NE 8th to 10th St (West Half Road Reconstruction). Traffic will be reduced to 1 lane.
- Time: 24 HRS
- Duration: 03/11/19 – 04/01/19
- Partial Lane Closure (2 Traffic Lanes) on NE 2nd Ave between NE 8th ST and NE 9th ST
- Demolition / Water and Sewer / Electrical Mains/ Irrigation Mains
- Time: 8AM to 4PM
- Duration 03/11/2019 to 04/01/2019
- Partial Closure on NE 8th St. Between NE 1st and NE 2nd Ave due to Gas line installation.
- MWC Luma
- Demolition of Unforeseen Concrete Foundations
- Grading Site to 9.00NGVD
- Haul Off of Site Soil and Demolition Soils
NOTE: All Concrete pours anticipated to start at 1am.