For your information, the following is a list of “Key” activities that will be occurring around the site over the next couple of weeks.
- Paramount:
- Partial Lane Closure on NE 10th St. between NE 1st Ave and NE 2nd Ave.:
- Duration: 05/01/19 – 06/30/19
- Time: from 7:30 AM to 6:30 PM
- Partial Lane closure; most eastern lanes on 1st Ave. between NE 8th and NE 10th Street
- Duration: 05/01/19 – 07/31/19
- Time: 24 Hours
- Building Enclosure at Podium continues
- Interior finishes continue
- Amenity deck continues
- Partial Lane Closure on NE 10th St. between NE 1st Ave and NE 2nd Ave.:
- Block D East:
- Amenity deck continues
- Installation of the metal fins started on the north elevation
- Off-site utilities installation along 2nd Avenue continues
- Partial Lane Closure (1 Traffic Lanes) on NE 2nd Ave between NE 8th ST and NE 10th ST
- Installation of Pavers
- Time: 8AM to 4PM
- Duration 06/24/19 – 06/28/19
- Site Work:
- 2 Lane closure on N Miami Ave. between 8th St. and R/R tracks.
- Excavation and installation of drainage
- Time: 8AM to 4PM
- Duration: 05/03/19 – 05/11/19
- Partial Lane and Side walk closure on N Miami Ave.
- Drainage and Electrical Work
- Time: 8AM to 4PM
- Duration: 06/24/19 -06/30/19
- 2 Lane closure on N Miami Ave. between 8th St. and R/R tracks.
- MWC Luma
- Installing tower production piles
- Installing tower sheet piles
- Start installing garage production piles
- Installing temp power
- Installing permanent wells
NOTE: All Concrete pours anticipated to start at 1am.