For your information, the following is a list of “Key” activities that will be occurring around the site over the next couple of weeks.
- Paramount:
- Villas window install continues
- Villa area Amenity deck construction continues
- Work by Others – Allegiance Crane for the NAP (Not by CoastalTishman)
- Two lane closure on NE 1 Ave. between NE 8th and NE 9th Street
- Dates: 02/10/20, 02/17/20 and 02/24/20
- Time: 10:00 PM to 06:00 AM
- Two lane closure on NE 1 Ave. between NE 8th and NE 9th Street
- D East
- Sidewalk partially closed on NE 2nd Ave. (West Side)
- Dates: 01/18/20 to 01/21/20
- Time: 08:00AM to 05:00PM
- Sidewalk partially closed on NE 2nd Ave. (West Side)
- MWC Luma
- Tower
- Forming and pouring verticals – daytime
- Forming Slabs – daytime
- Pouring Slabs
- FRP Verticals at Garage
- All Concrete Pours start at 04:00 AM
- Tower