For your information, the following is a list of “Key” activities that will be occurring around the site over the next couple of weeks.
- Paramount:
- Concrete pours at the amenity deck and pools is in progress.
- Window installation continues.
- Wall layout, framing, and interior finishes are ongoing.
- Elevator bracket and rails installation ongoing.
- North and South Hoist take down 12/19/18 and 01/20/19.
- NE 10th St. full Road closure:
- Duration: 01/02/19 -01/30/19
- Time: from 7:30 AM to 6:30 PM
- 7th Street Apartments Project:
- Retail Window installation continues.
- Interior Punchout continues.
- Material deliveries on weekends.
- Façade panels install continues.
- Block D East:
- Elevators Installation is ongoing.
- Stucco work continues.
- Doors and door frames installations continue.
- Installation Façade Metal panels and sub framing on the north elevation.
- Installation of the steel supporting members for the louvers.
- Installation of the temporary walls started.
- Site Work:
- Full Road closure on NE 1st Ave between R/R and 8th St.
- Duration 01/14/19 to 01 /16/19
- Full Road closure on NE 1st Ave between R/R and 8th St.
-
- Daily Road Closure as needed on NE 8th St. Between NE 1st and NE 2nd Ave
- Duration 01/14/2019 to 01/25/2019
- Daily Road Closure as needed on NE 8th St. Between NE 1st and NE 2nd Ave
NOTE: All Concrete pours anticipated to start at 1am.