For your information, the following is a list of “Key” activities that will be occurring around the site over the next couple of weeks.

  1. Paramount:
    •  Concrete pours at the amenity deck and pools is in progress.
    • Window installation continues.
    • Wall layout, framing, and interior finishes are ongoing.
    • Elevator bracket and rails installation ongoing.
    • North and South Hoist take down 12/19/18 and 01/20/19.
    • NE 10th St. full Road closure:
      • Duration: 01/02/19 -01/30/19
      • Time: from 7:30 AM to 6:30 PM
  2.  7th Street Apartments Project:
    • Retail Window installation continues.
    • Interior Punchout continues.
    • Material deliveries on weekends.
    • Façade panels install continues.
  3. Block D East:
    • Elevators Installation is ongoing.
    • Stucco work continues.
    • Doors and door frames installations continue.
    • Installation Façade Metal panels and sub framing on the north elevation.
    • Installation of the steel supporting members for the louvers.
    • Installation of the temporary walls started.
  4. Site Work:
    • Full Road closure on NE 1st Ave between R/R and 8th St.
      • Duration 01/14/19 to 01 /16/19
    • Daily Road Closure as needed on NE 8th St. Between NE 1st and NE 2nd Ave
      • Duration 01/14/2019 to 01/25/2019

NOTE: All Concrete pours anticipated to start at 1am.