For your information, the following is a list of “Key” activities that will be occurring around the site over the next couple of weeks.

  1. Block F West
  • Construction is ongoing from 12/01/2023 to 12/01/2025.
  • A fence around the lot is installed.
  • 1ST Ave Sidewalk around the property is open.
  • 8 ST sidewalk will be closed temporary during utility work in February.
  • 8 ST Asphalt and Street repairs will be performed in February.
  • Remove fence 10/2024.
  • Finish Construction 12/2024.

2. Private Improvements Main Plaza

  • Construction is ongoing from 12/01/2023 to 12/01/2025.
  • A fence around the lot is installed.
  • 1ST Ave Sidewalk around the property is open.
  • Pedestrian paseo is open to the public.
  • Remove fence 10/2024.
  • Finish Construction 12/2024.