For your information, the following is a list of “Key” activities that will be occurring around the site over the next couple of weeks.
1. F-East
- Structural steel erection continues
- Metal deck installation continues
- 2nd floor metal deck concrete pour scheduled for second week of August, 2021
2. Private Improvement Areas
- 1st street, we continue to install pavers and will install Landscape in August. The sidewalk is temporarily closed.
- 2nd street, we continue to install pavers and will install Landscape in August. The sidewalk is temporarily closed.
- Half of 7ST street, we continue to install pavers and will install Landscape in August. The sidewalk is temporarily closed.
3. Block H and Bezel
- STO Install for Art Wall on West Elevation on going
- Interior Garage Striping on going
- Garage Louver Installation on going
- Finalizing details on Lvl 13 Roof
- Elevators being adjusted and phone line installation on going