For your information, the following is a list of “Key” activities that will be occurring around the site over the next couple of weeks.
- Paramount:
- Level 7 Villas and Tennis Court Construction continues
- Ground Level – Paver Replacement at Main Driveway
- Dates: 03/30/20 – 04/21/20
- Hours: 08:00 AM to 06:00 PM
- D-East
- Site Work
- NE 8 Street from NE 1 Ave. to NE 2 Ave (North Side) – Sidewalk Closure for Paver tray Installation and repair.
- Dates: 03/30/20 to 04/10/20
- Times: 08:00 AM – 04:00 PM
- NE 8 Street from NE 1 Ave. to NE 2 Ave (North Side) – Sidewalk Closure for Paver tray Installation and repair.
- MWC Luma
- Tower / Garage
- Forming and pouring verticals – daytime
- Concrete Slab Pours
- FRP Verticals at Garage
- MEP Installation Underground
- Block installation at garage and tower
- Window Installation, MEP rough in and framing continues
- Temporary Hours of construction 08:00 AM to 06:00 PM
- Tower / Garage