For your information, the following is a list of “Key” activities that will be occurring around the site over the next couple of weeks.

  1. Paramount:
    • Full Street Closure: NE 8th Street between NE 1st and 2nd Ave.
      • Duration: 10/07/19 – 10/31/19
      • Time: from 8:00 AM to 4:00 PM
    • Interior finishes continue
    • Façade panel installation continue
    • Amenity deck continues
    • Single lane closure: NE 1 Ave between NE 8 and 10 Street
      • Duration: 10/07/19 – 10/31/19
      • Time: 08:00 AM – 05:00 PM
  2. Site work:
    • Partial Closure: NE 8 Street between NE 1 and 2 Ave.
      • Duration: 10/21/19 – 10/22/19
      • Times: 8:00 AM – 5:00PM
    • Partial Closure: NE 1 Ave between NE 8 and 10 street
      • Duration: 10/22/19 -10/23/19
      • Times: 8:00 AM – 5:00 PM
    • Partial Closure: NE 10 street between NE 1 and 2 Ave.
      • Duration: 10/23/19 -10/24/19
      • Times: 8:00 AM – 5:00 PM
    • Partial Closure: NE 2 Ave between NE 1 Ave and Biscayne Blvd.
      • Duration: 10/24/19 -10/25/19
      • Times: 8:00 AM – 5:00 PM
  3. MWC Luma
    • Tower
      • Forming and pouring verticals – daytime
      • Forming Slabs – daytime 46 NE 6 Street Miami, FL 33132
      • Pouring Slabs
        • Start Time: 03:00 AM
        • Dates: 10/22/19 and 10/30/19
    • Garage
      • FRP Verticals
      • Backfilling and hauling off excess dirt
      • Demobilizing dewatering equipment
      • Shoring material delivery and set up daily
      • Pouring Garage Slabs –
        • Start Time: 03:00 AM
        • Date: 10/30/19