For your information, the following is a list of “Key” activities that will be occurring around the site over the next couple of weeks.

  1. Paramount:
    • Full Street Closure: NE 8th Street between NE 1st and 2nd Ave.
      • Duration: 09/17/19 – 09/27/19
      • Time: from 8:00 AM to 4:00 PM
    • Interior finishes continue
    • Façade panel installation continue
    • Amenity deck continues
  2. Site work
    • 9/18 Partial Closures starting at 9:00 PM – 6:00 AM
      • Milling NE 9th ST from N Miami Ave to NE 1st Ave
      • Prep for NE 1st Ave from RR Tracks to NE 10th ST
      • Final Lift of NE 9th ST from NE 1st Ave to N Miami Ave
      • Final Lift on NE 8th ST from NE 1st Ave to NE 2nd Ave
    • 9/19 & 9/20 – Partial Closures starting at 9:00 PM – 6:00 AM
      • Final lift of NE 1st Ave from NE 6th ST to NE 10th ST
      • Milling of NE 2nd Ave from NE 10th ST to RR Tracks
    • 9/22 and 9/23 – Partial Closures starting at 9:00 PM – 6:00 AM
      • Final Lift of NE 2nd Ave from NE 10th ST to RR Tracks
  3. MWC Luma
    • Tower
      • Forming and pouring verticals – daytime
      • Backfilling foundations
      • Temp Power Install ongoing
      • Decking starting around 09/25/19
    • Garage
      • Excavating foundations
      • Chipping piles
      • FRP foundations
      • FRP verticals