For your information, the following is a list of “Key” activities that will be occurring around the site over the next couple of weeks.
- Paramount:
- Full Street Closure: NE 8th Street between NE 1st and 2nd Ave.
- Duration: 09/17/19 – 09/27/19
- Time: from 8:00 AM to 4:00 PM
- Interior finishes continue
- Façade panel installation continue
- Amenity deck continues
- Full Street Closure: NE 8th Street between NE 1st and 2nd Ave.
- Site work
- 9/18 Partial Closures starting at 9:00 PM – 6:00 AM
- Milling NE 9th ST from N Miami Ave to NE 1st Ave
- Prep for NE 1st Ave from RR Tracks to NE 10th ST
- Final Lift of NE 9th ST from NE 1st Ave to N Miami Ave
- Final Lift on NE 8th ST from NE 1st Ave to NE 2nd Ave
- 9/19 & 9/20 – Partial Closures starting at 9:00 PM – 6:00 AM
- Final lift of NE 1st Ave from NE 6th ST to NE 10th ST
- Milling of NE 2nd Ave from NE 10th ST to RR Tracks
- 9/22 and 9/23 – Partial Closures starting at 9:00 PM – 6:00 AM
- Final Lift of NE 2nd Ave from NE 10th ST to RR Tracks
- 9/18 Partial Closures starting at 9:00 PM – 6:00 AM
- MWC Luma
- Tower
- Forming and pouring verticals – daytime
- Backfilling foundations
- Temp Power Install ongoing
- Decking starting around 09/25/19
- Garage
- Excavating foundations
- Chipping piles
- FRP foundations
- FRP verticals
- Tower