For your information, the following is a list of “Key” activities that will be occurring around the site over the next couple of weeks.
1. F-East
- Fireproofing of steel columns on-going
- CMU block installation ongoing
- MEP rough installation ongoing
- GFRC installation to start mid-November
- Glass installation to start mid- November
- Roofing to start mid-November
- Water and sewer connections to start week of November 8. Expect some road closures on NE 8 street, between 1st ave and 2nd
2. Private Improvement Areas
- 1st Ave: Landscape was installed. In November, we will install pavers. The sidewalk is temporarily closed.
- 2nd Ave: Landscape, Pavers and lighting were installed. In November, we will install polymeric sand. The sidewalk is temporarily closed.
- Half of 7ST street: Landscape, Pavers and lighting were installed. In November, we will install polymeric sand. The sidewalk is temporarily closed.
- Bezel Drop Off: Landscape and Pavers were installed. In November, we will install polymeric sand. The area is temporarily closed.
3. Block H Garage and Retail
- STO Crotique Install on Art Wall Framing on West Elevation – COMPLETE
- Garage – Lvls 2-11 – Punching Out for Final Completion
- Elevators 6 & 7 / Elev. 8 & 9 – Final Inspections
- North Elevation Exterior Lights Installed – Installation Complete Adjustment On-going
- East Portal Base – Lights on Going
4. Bezel Apartments – Now Leasing