For your information, the following is a list of “Key” activities that will be occurring around the site over the next couple of weeks.

  1. Paramount:
    • Partial Lane Closure on NE 8th St. corner with 1st Ave.
      • Duration: 07/15/19 – 07/30/19
      • Time: from 7:30 AM to 6:30 PM
    • Partial Lane closure; most eastern lanes on 1st Ave. between NE 8th and NE 10th Street
      • Duration: 05/01/19 – 08/02/19
      • Time: 7:30 AM to 6:00 PM
    • Interior finishes continue
    • Amenity deck continues
  2. Block D East:
    • Amenity deck continues
    • Installation of the metal fins started on the north elevation
    • Off-site utilities installation along 2nd Avenue continues
  3. Site Work:
    • N Miami Ave from NE 8th ST to RR Tracks – Sidewalk Closure.
      • Time: 8AM to 4PM
      • Duration: 07/08/19 – 07/19/19
    • NE 1st Ave from NE 6th ST to RR Tracks – Sidewalk Closure
      • Time: 8AM to 4PM
      • Duration: 07/08/19 – 07/12/19
  4. MWC Luma
    • Installing garage production piles
    • Breaking down 888 on Monday 7/1
    • Chipping piles
    • Forming, Rebar and pouring tower foundations
    • Installing dewatering equipment

NOTE: All Concrete pours anticipated to start at 1am.