For your information, the following is a list of “Key” activities that will be occurring around the site over the next couple of weeks.
- Paramount:
- Partial Lane Closure on NE 8th St. corner with 1st Ave.
- Duration: 07/15/19 – 07/30/19
- Time: from 7:30 AM to 6:30 PM
- Partial Lane closure; most eastern lanes on 1st Ave. between NE 8th and NE 10th Street
- Duration: 05/01/19 – 08/02/19
- Time: 7:30 AM to 6:00 PM
- Interior finishes continue
- Amenity deck continues
- Partial Lane Closure on NE 8th St. corner with 1st Ave.
- Block D East:
- Amenity deck continues
- Installation of the metal fins started on the north elevation
- Off-site utilities installation along 2nd Avenue continues
- Site Work:
- N Miami Ave from NE 8th ST to RR Tracks – Sidewalk Closure.
- Time: 8AM to 4PM
- Duration: 07/08/19 – 07/19/19
- NE 1st Ave from NE 6th ST to RR Tracks – Sidewalk Closure
- Time: 8AM to 4PM
- Duration: 07/08/19 – 07/12/19
- N Miami Ave from NE 8th ST to RR Tracks – Sidewalk Closure.
- MWC Luma
- Installing garage production piles
- Breaking down 888 on Monday 7/1
- Chipping piles
- Forming, Rebar and pouring tower foundations
- Installing dewatering equipment
NOTE: All Concrete pours anticipated to start at 1am.