Construction Update Week of December 6, 2019

December 6, 2019

For your information, the following is a list of “Key” activities that will be occurring around the site over the next couple of weeks.

  1. Paramount:
    • Interior finishes continue
    • Façade panel installation continue
    • Amenity deck continues
    • One lane closure: NE 1 Ave between NE 8 and 10 Street
      • Duration: 11/27/19 – 12/16/19
      • Time: 08:00 AM – 03:00 PM
  2. MWC Luma
    • Tower
      • Forming and pouring verticals – daytime
      • Forming Slabs – daytime
      • Pouring Slabs
      • FRP Verticals at Garage
      • All Concrete Pours start at 04:00 AM

CommunityPost 12.6.2019 944073

CommunityPost 12.6.2019 944072

CommunityPost 12.6.2019 944071

CommunityPost 12.6.2019 944070