For your information, the following is a list of “key” activities that will be occurring around the site over the next couple of weeks.

1. F-East 

  • CMU block installation ongoing 
  • MEP rough installation ongoing 
  • GFRC installation on going on north façade – Expect some road closures on NE 8 street, between 1st ave and 2nd ave.
  • Glass installation to starts on south façade December 8, 2021 
  • Roofing on going and scheduled to be complete before the end of the year 
  • Sewer lateral connection completed connections completed. 

2. Private Improvement Areas 

  • 1st Ave: Pavers was installed in November. The sidewalk is open to the public. 
  • 2nd Ave: Landscape, Pavers and lighting were installed in November. The sidewalk is temporarily closed. 
  • Half of 7ST street: The work is completed. The area is temporarily closed, end of December it is going to be open to the public. 
  • Bezel Drop Off: The work is completed. The area is temporarily closed, end of December it is going to be open to the public.

3. Block H Garage and Retail  

  • TCO 1 for Lvl 1-26 Tower, Garage, and Retail – 12.01.2021 
  • Garage Lvl 2-11, Elevators 6-9  –Complete & Punch Out On going  
  • North Elevation Exterior Lights Installed – Installation Complete Adjustment On-going  
  • East Portal Base – Lights on Going  
  • West Art Wall Lighting – Installed   

4. Bezel Apartments – Now Leasing