For your information, the following is a list of “Key” activities that will be occurring around the site over the next couple of weeks.

  1. Paramount:
    • Partial Lane Closure on NE 8th St. corner with 1st Ave.
      • Duration: 08/01/19 – 08/31/19
      • Time: from 7:30 AM to 6:30 PM
    • Partial Lane closure; most eastern lane on 1st Ave. between NE 8th and NE 10th Street
      • Duration: 08/01/19 – 08/31/19
      • Time: 7:30 AM to 6:00 PM
    • Interior finishes continue
    • Amenity deck continues
  2. Block D East:
    • Sidewalk Partial closure – NE 2 Ave between NE 8 Street and NE 9 Street
      • Time: 8PM – 5AM
      • Duration: 08/12/19 – 08/26/19
    • Sidewalk Partial Closure – NE 2nd Ave Between NE 8 Street and NE 9 Street
      • Time: 8AM – 4PM
      • Duration: 08/07/19 – 08/12/19
    • Continue punch list throughout.
  3. Site Work:
    •  N Miami Ave from NE 8th ST to RR Tracks – Sidewalk Closure.
      • Time: 8AM to 4PM
      • Duration: 08/05/19 – 08/30/19
    • NE 10th ST from NE 2nd Ave to NE 1st Ave – Two Oak Plantings in Landscape Beds
      • Street Closure on 08.07.19 (2 East Bound Lanes)
    • NE 2nd Ave and NE 7th ST (East Half) – Street Closure East / West Bound Lane – Day work
      • Time: 8AM – 4PM
      • Duration: 08/07/19 – 08/09/19
    • Sidewalk Closure – NE 2 Ave and NE 10 Street (East Half)
      • Time: 8AM – 4PM
      • Duration 08/12/19 – 08/13/19
    • Street Closure – NE 10th ST from NE 2nd Ave to NE 1st Ave (BVIEW)
      • Two Oak Plantings in Landscape Beds
      • Duration: 08/07/19 8AM – 4PM
  4. MWC Luma
    • Chipping piles
    • Forming, Rebar and pouring tower foundations
    • Mat Pour – no street closure required
      • Duration: Start 08/24/19 at Mid-night 12:00 AM – 08/24/19 05:00PM

NOTE: All concrete pour activities will start at Mid-night.