For your information, the following is a list of “Key” activities that will be occurring around the site over the next couple of weeks.

  1. Paramount:
    • Level 7 Villas and Tennis Court Construction continues
    • Ground Level – Paver Replacement at Main Driveway
      • Dates: 03/30/20 – 04/21/20
      • Hours: 08:00 AM to 06:00 PM
  2. D-East
  3. Site Work
    • NE 8 Street from NE 1 Ave. to NE 2 Ave (North Side) – Sidewalk Closure for Paver tray Installation and repair.
      • Dates: 03/30/20 to 04/10/20
      • Times: 08:00 AM – 04:00 PM
  4. MWC Luma
    • Tower / Garage
      • Forming and pouring verticals – daytime
      • Concrete Slab Pours
      • FRP Verticals at Garage
      • MEP Installation Underground
      • Block installation at garage and tower
      • Window Installation, MEP rough in and framing continues
      • Temporary Hours of construction 08:00 AM to 06:00 PM