Update: Road Closure Information

For your information, the following is a list of “Key” activities that will be occurring around the site over the next couple of weeks.

1. Paramount:

a. Concrete pours continue; currently pouring levels 40 and up.
b. Window installation continues to follow concrete.
c. Wall layout, framing, and interior finishes are ongoing.
d. Full closure of NE 10th St. between NE 1st and 2nd Ave. for a Sewer connection.

• Closure Dates: 02/05/18 to 02/09/18.
• Closure time: 7AM to 4PM.

2. 7th Street Apartments Project:

a. Concrete pour of interior core continues – Levels 38 and up.
b. Concrete pours – garage deck continues.
c. Window installation continues to follow concrete.
d. Interior framing continues.
e. MEP rough-ins continue in apartment units.

3. Block D East:

a. Forming and placing Concrete on Level 8 amenities deck.
b. Slab on grade continues.
c. Continue MEP installation throughout the building.
d. Commencing construction of Bungalows.

4. Site Work:

a. Drainage installation along NE 1st Ave. between 8th and 6th street (East side).

• Parking lane and side walk closure on NE 1st Ave.
• Closure Duration: 02/05/18 – 02/09/18 8PM – 5AM.

b. Drainage Installation along NE 1st Ave. between 8th and 9th street.

• Full closure of 1st Ave.
• Closure duration 02/12/18 – 02/16/18 8PM – 5AM

NOTE: All Concrete pours anticipated to start at 1am.