Update: Road Closure Information

For your information, the following is a list of “Key” activities that will be occurring around the site over the next couple of weeks.

1. Paramount:

a. Concrete pours continue; currently pouring levels 37 and up
b. Window installation continues to follow concrete.
c. Wall layout, framing, and interior finishes are ongoing.
d. Crane Jump – MOT – Full street closure of NE 8th St. between NE 1st and 2nd Ave.

    • Closure Dates: January 20th and 21st.
    • Closure time: 7AM to 5PM

2. 7th Street Apartments Project:

a. Concrete pour continues in tower– Levels 42 and up.
b. Concrete pours – garage deck continues.
c. Window installation continues – level 25.
d. Interior framing continues.
e. MEP rough-ins continue in apartment units.

3. Block D East:

a. Forming and placing Concrete on Level 7M and 8 of amenities deck.
b. Forming and placing Concrete on Level 8 amenities deck.
c. Beginning slab on grade.
d. Continue MEP installation throughout the building.

4. Site Work:

a. Drainage installation along NE 10th St. between NE 1st Ave to NE 2nd Ave.

    • Partial lane closure on NE 10th St.
    • Closure Duration: January 9th thru January 19th from 7:00AM to 4:00PM.

b. Drainage installation along NE 1st Ave. between 6th and 8th street (West side).

    • Partial lane closure on NE 1st Ave.
    • Closure Duration: January 22nd to February 16th from 8PM – 5AM.

NOTE: All Concrete pours anticipated to start at 1am.

2 day closure

NE 1st AVE Closure

NE 10th ST Closure