For your information, the following is a list of “Key” activities that will be occurring around the site over the next couple of weeks.

  1. Paramount:
    • Partial Lane Closure on NE 8th St. corner with 1st Ave.
      • Duration:08/01/19 – 09/20/19
      • Time: from 7:30 AM to 6:30 PM
    • Full Street Closure: NE 8th Street between NE 1st and 2nd Ave.
      • Duration: 09/05/19– 09/07/19
      • Time: from 8:00 AM to 4:00 PM
    • Partial Lane closure; two lanes (West Side) on 1st Ave. between NE 8th and NE 10th Street for the placement of a crane.
      • Duration:09/09/19– 09/13/19
      • Time:8:00 AM to 4:00 PM
    • Full Closure – NE 8th Street between NE 1 Ave and NE 2 Ave
      • Duration: 09/14/19 – 09/19/19
      • Time:8:00 AM to 4:00 PM
    • Interior finishes continue
    • Façade panel installation continues
    • Amenity deck continues
  2. MWC Luma
    • Site
      • Reinstalling vision screen
    • Tower
      • Forming and pouring verticals – daytime
      • Pulling sheet piles – daytime
    • Garage
      • Excavating foundations
      • Chipping piles
      • FRP foundations
      • FRP verticals
  3. Street Closures
    • Starting Sunday 9/15 to Wednesday 9/18 from 9PM to 6AM
      • Milling N Miami Ave from RR Tracks to NE 9th ST
      • Milling NE 9th ST from N Miami Ave to NE 1st Ave
      • Milling NE 1st Ave from RR Tracks to NE 6th ST
      • Final Lift on NE 8th ST from NE 1st Ave to NE 2nd Ave
      • Final Lift of NE 10th ST from NE 1st Ave to NE 2nd Ave
    • 9/16 Partial Closures starting at 9:00 PM – 6:00 A
      • Final lift of NE 1st Ave from NE 6th ST to NE 10th ST
    • 9/17 Partial Closures starting at 9:00 PM – 6:00 AM
      • Milling of NE 2nd Ave from NE 10th ST to RR Tracks
      • Final Lift of N Miami Ave from RR Tracks to NE 9th ST
      • Final Lift of NE 9th ST from NE 1st Ave to N Miami Ave
    • 9/18 Partial Closures starting at 9:00 PM – 6:00 AM
      • Final Lift of NE 2nd Ave