Construction Update Week of September 16, 2019

For your information, the following is a list of “Key” activities that will be occurring around the site over the next couple of weeks.

1. Paramount:

a. Full Street Closure: NE 8th Street between NE 1st and 2nd Ave.

• Duration: 09/17/19 – 09/27/19

• Time: from 8:00 AM to 4:00 PM

b. Interior finishes continue

c. Façade panel installation continue

d. Amenity deck continues

2. Site work

a. 9/18 Partial Closures starting at 9:00 PM – 6:00 AM

• Milling NE 9th ST from N Miami Ave to NE 1st Ave

• Prep for NE 1st Ave from RR Tracks to NE 10th ST

• Final Lift of NE 9th ST from NE 1st Ave to N Miami Ave

• Final Lift on NE 8th ST from NE 1st Ave to NE 2nd Ave

b. 9/19 & 9/20 – Partial Closures starting at 9:00 PM – 6:00 AM

• Final lift of NE 1st Ave from NE 6th ST to NE 10th ST

• Milling of NE 2nd Ave from NE 10th ST to RR Tracks

c. 9/22 and 9/23 – Partial Closures starting at 9:00 PM – 6:00 AM

• Final Lift of NE 2nd Ave from NE 10th ST to RR Tracks

3. MWC Luma

a. Tower

• Forming and pouring verticals – daytime

• Backfilling foundations

• Temp Power Install ongoing

• Decking starting around 09/25/19

b. Garage

• Excavating foundations

• Chipping piles

• FRP foundations

• FRP verticals