Construction Update Week of October 28, 2018

For your information, the following is a list of “Key” activities that will be occurring around the site over the next couple of weeks.

1. Paramount:

a. Concrete pours continue; currently pouring level 61.
b. Concrete pours at the amenity deck has started.
c. Window installation on levels 50 and 51.
d. Wall layout, framing, and interior finishes are ongoing.
e. Elevator bracket and rails installation ongoing.
f. Elevator frames from 2nd thru 61st floors continue.

2. 7th Street Apartments Project:

a. Window installation continues in Garage and retail areas.
b. Interior framing and MEP rough-ins continue in levels 1st and 10th.
c. CMU installation in Garage continues.
d. Material deliveries on weekends.
e. Façade panels install continues.
f. Tile work on pool deck continue.
g. Ground Level installation begins.

3. Block D East:

a. MEP installation continues throughout the building.
b. Masonry installation continues throughout the building.
c. Elevators Installation is ongoing.
d. Stucco work continues.
e. Doors and door frames installations continue.

4. Site Work:

a. NE 8th St between N Miami Ave and NE 1st Ave – South Side – Sidewalk Reconstruction:

• Single Lane Closure
• Date: 10/26/18 -11/02/18

b. Sidewalk paver installation NE 1st Ave Between R/R and NE 9th St
c. Paver installation 7th St Promenade from Block G north
d. Water Feature Drainage and structure continues
e. Sidewalk paver installation NE 8th St Between NE 1st and N. Miami
f. Site security duct bank, crossing Ne 8th St between Ne 1st Ave and NE 2nd Ave

• Full Road closure
• Date: 10/29-10/30

g. NE 1st Ave between RR Tracks and NE 8th ST – Road Reconstruction and Curb– East Side

• Single Lane closure:
• Dates: 10/26/18 – 11/01/18

NOTE: All Concrete pours anticipated to start at 1am.