Construction Update Week of October 21, 2019

For your information, the following is a list of “Key” activities that will be occurring around the site over the next couple of weeks.

1. Paramount:

a. Full Street Closure: NE 8th Street between NE 1st and 2nd Ave.

• Duration: 10/07/19 – 10/31/19

• Time: from 8:00 AM to 4:00 PM

b. Interior finishes continue

c. Façade panel installation continue

d. Amenity deck continues

e. Single lane closure: NE 1 Ave between NE 8 and 10 Street

• Duration: 10/07/19 – 10/31/19

• Time: 08:00 AM – 05:00 PM

2. Site work:

a. Partial Closure: NE 8 Street between NE 1 and 2 Ave.

• Duration: 10/21/19 – 10/22/19

• Times: 8:00 AM – 5:00PM

b. Partial Closure: NE 1 Ave between NE 8 and 10 street

• Duration: 10/22/19 -10/23/19

• Times: 8:00 AM – 5:00 PM

c. Partial Closure: NE 10 street between NE 1 and 2 Ave.

• Duration: 10/23/19 -10/24/19

• Times: 8:00 AM – 5:00 PM

d. Partial Closure: NE 2 Ave between NE 1 Ave and Biscayne Blvd.

• Duration: 10/24/19 -10/25/19

• Times: 8:00 AM – 5:00 PM

3. MWC Luma

a. Tower

• Forming and pouring verticals – daytime

• Forming Slabs – daytime 46 NE 6 Street Miami, FL 33132

• Pouring Slabs

• Start Time: 03:00 AM

• Dates: 10/22/19 and 10/30/19

b. Garage

• FRP Verticals

• Backfilling and hauling off excess dirt

• Demobilizing dewatering equipment

• Shoring material delivery and set up daily

• Pouring Garage Slabs –

• Start Time: 03:00 AM

• Date: 10/30/19