Construction Update Week of October 01, 2018

For your information, the following is a list of “Key” activities that will be occurring around the site over the next couple of weeks.

1. Paramount:

a. Concrete pours continue; currently pouring level 61.
b. Concrete pours at the amenity deck has started.
c. Window installation continues to follow concrete.
d. Wall layout, framing, and interior finishes are ongoing.
e. Elevator bracket and rails installation ongoing.
f. Elevator frames from 2nd thru 48th floors continue.
g. Full closure of NE 1st Ave and North side of 10th St.

• Duration: 10/09/18 from 9PM to 4AM

h. Full closure of NE 8th ST between NE 1st Ave. and 2nd Ave.

• From 9AM to 3PM

2. 7th Street Apartments Project:

a. Window installation continues in Garage and retail areas.
b. Interior framing and MEP rough-ins continue in levels 1st and 10th.
c. CMU installation in Garage continues.
d. Material deliveries on weekends.
e. Façade panels install continues.
f. Tile work on pool deck continue.
g. Ground Level installation begins.

3. Block D East:

a. MEP installation continues throughout the building.
b. Miscellaneous metal installation.
c. Masonry installation continues throughout the building.
d. Barrier cable installation.
e. Elevators Installation is ongoing.
f. Stucco work starting on the east site elevation.

4. Site Work:

a. Sidewalk reconstruction NE 10th St. between 1st and 2nd Ave.

• Single Lane Street Closure
• Dates: 09/27/18 – 10/10/18.

b. NE 8th St between N Miami Ave and NE 1st Ave – South Side – Curb and Gutter Reconstruction:

•Full Road Closure in conjunction with TECO Gas install.
• Dates: 09/26/18 – 10/05/18

c. NE 8th St between N Miami Ave and NE 1st Ave – South Side – Sidewalk Reconstruction:

• Single Lane Closure
• Date: 10/06/18 -10/26/18

d. N. Miami Ave. between RR Tracks and NE 8th St.- Drainage

• 2 lane Closure
• Dates: 10/08/18 – 10/26/18

e. NE 1st Ave between RR Tracks and NE 8th ST – Sidewalk Reconstruction – West Side

• Parking Lane Only closure:
• Dates: 09/26/18 – 10/12/18

NOTE: All Concrete pours anticipated to start at 1am.