Construction Update Week of November 1, 2019

For your information, the following is a list of “Key” activities that will be occurring around the site over the next couple of weeks.

1. Paramount:

a. Full Street Closure: NE 8th Street between NE 1st and 2nd Ave.

• Duration: 11/11/19 – 11/18/19

• Time: from 8:00 AM to 4:00 PM

b. Interior finishes continue

c. Façade panel installation continue

d. Amenity deck continues

e. Two lane closure: NE 1 Ave between NE 8 and 10 Street

• Duration: 10/28/19 – 11/05/19

• Time: 08:00 AM – 03:00 PM

f. One lane closure: NE 1 Ave between NE 8 and 10 Street

• Duration: 11/05/19 – 11/26/19

• Time: 08:00 AM – 04:00 PM

2. Site work:

a. Partial Closure: NE 8 Street between NE 1 and 2 Ave.

• Duration: 10/21/19 – 11/08/19

• Times: 8:00 AM – 3:00PM

b. Partial Closure: NE 1 Ave between NE 8 and 10 street

• Duration: 10/22/19 -11/08/19

• Times: 8:00 AM – 3:00 PM

c. Partial Closure: NE 10 street between NE 1 and 2 Ave.

• Duration: 10/23/19 -11/08/19

• Times: 8:00 AM – 3:00 PM

d. Partial Closure: NE 2 Ave between NE 1 Ave and Biscayne Blvd.

• Duration: 10/24/19 -11/08/19

• Times: 8:00 AM – 3:00 PM

3. MWC Luma

a. Tower

• Forming and pouring verticals – daytime

• Forming Slabs – daytime

• Pouring Slabs

• FRP Verticals at Garage

• Concrete Pours schedule for the following week

• Date: 11/06/19 – Start Time: 02:00 AM to 7 AM

• Date: 11/09/19 thru 11/15/19 – Start Time: 04:00 AM