Construction Update Week of November 5, 2017

For your information, the following is a list of “Key” activities that will be occurring around the site over the next couple of weeks.

1. Paramount:

a. Concrete pours continue; currently pouring levels 25 and up.
b. Window installation continues to follow concrete.
c. Wall layout, framing, and interior finishes are ongoing.
d. Steel, Metal and Drywall deliveries continue.
e. Crane Jump – MOT – Full Street Closure of NE 8th St between NE 1st and 2nd ave.

• Closure days: November 18th and 19th
• Closure Time: from 7AM to 4PM

2. 7th Street Apartments Project:

a. Concrete pour continues in tower– Levels 32 and up.
b. Concrete pours – garage deck levels 6.
c. Window installation continues – levels 19 and 20.
d. Interior framing continues.

3. Retail at Miami Worldcenter (Block D East):

a. Placing level 8 – East side.
b. Placing Level 5 West side.
c. Forming Level 4.
d. Continue UG plumbing installation for SOG.

NOTE: All Concrete pours anticipated to start at 1am.