Construction Update Week of November 19, 2018

For your information, the following is a list of “Key” activities that will be occurring around the site over the next couple of weeks.

1. Paramount:

a. Concrete pours at the amenity deck and pools is in progress.
b. Window installation continues
c. Wall layout, framing, and interior finishes are ongoing
d. Elevator bracket and rails installation ongoing
e. Elevator frames from 2nd thru 61st floors continue

2. 7th Street Apartments Project:

a. Retail Window installation continues.
b. Interior Punchout began.
c. Material deliveries on weekends.
d. Façade panels install continues.
e. Tile work on pool deck continues.

3. Block D East:

a. MEP installation continues throughout the building.
b. Masonry installation continues throughout the building.
c. Elevators Installation is ongoing.
d. Stucco work continues.
e. Doors and door frames installations continue.

4. Site Work:

a. NE 8th St between N Miami Ave and NE 1st Ave – South Side – Sidewalk Reconstruction
b. Sidewalk paver installation NE 1st Ave Between NE 8th and NE 9th St.
c. Water Feature Coping and Tile Installation continues.
d. Sidewalk paver installation NE 8th St Between NE 1st and N. Miami – South Side.
e. NE 1st Ave between RR Tracks and NE 8th ST – East side sidewalk reconstruction

• Single Lane closure

NOTE: All Concrete pours anticipated to start at 1am.