Construction Update Week of May 7, 2018

For your information, the following is a list of “Key” activities that will be occurring around the site over the next couple of weeks.

1. Paramount:

a. Concrete pours continue; currently pouring levels 49 and up.
b. Window installation continues to follow concrete.
c. Wall layout, framing, and interior finishes are ongoing.
d. Elevator bracket and rails installation ongoing.

2. 7th Street Apartments Project: On Wednesdays the pours are taking place from 8PM to 11PM.

a. Pool Deck – interstitial deck planter walls and framing of pool continues.
b. Window installation continues on levels 40 through 43.
c. Interior framing and MEP rough-ins continue in apartment units.
d. CMU installation in Garage.
e. Location: Partial lane closure on N. Miami Ave. between NW 6th St. and 8th St. by FPL.

• Duration: 03/29/18 thru 06/29/18
• Time of closure: 9PM to 8AM.

3. Block D East:

a. Forming roof top pools continues.
b. Slab on grade continues.
c. Continue MEP installation throughout the building and underground.
d. Handrail installation.
e. Formwork, rebar, pour concrete at Level 2 Mechanical opening.
f. Masonry installation Level 1 and Level 2 EMR’s.

4. Site Work:

a. Drainage installation along NE 8th St. between 1st and 2nd Ave. (South side).

• Full Street Closure dates: 04/11/18 – 05/18/18
• Time of Closure: 8:30Am – 4:30PM.

5. Block G: Road Closures

  • Reason for the closure: Directional Bore for Conduits
  • Location: 2 lane closure on the west side of North Miami Avenue between NW 6th St and NW 8th St
  • Duration (dates) Starting Friday 11th to Tuesday 15th.
  • Time: 7:00 AM – 7:00 PM

NOTE: All Concrete pours anticipated to start at 1am.