Construction Update Week of May 6, 2019

For your information, the following is a list of “Key” activities that will be occurring around the site over the next couple of weeks.

1. Paramount:

a. Partial Lane Closure on NE 10th St. between NE 1st Ave and NE 2nd Ave.:

    • Duration: 05/01/19 – 05/31/19
    • Time: from 7:30 AM to 6:30 PM

b. Partial Lane closure; two most eastern lanes on 1st Ave. between NE 8th and NE 10th Street.

    • Duration: 05/01/19 – 05/31/19
    • Time: 24 Hours

c. Building Enclosure at Podium continues
d. Interior finishes continue
e. Amenity deck continues

2. Block D East:

a. Elevators testing is ongoing and nearing completion.
b. Installation of the metal fins started on the north elevation.
c. Installation of the steel supporting members for the louvers continues.
d. Off-site utilities installation along 2nd Avenue continues.

3. Site Work:

a. 2 Lane closure on N Miami Ave. between 8th St. and R/R tracks.

    • Excavation and installation of drainage
    • Time:  8AM to 4PM
    • Duration 05/03/19 – 05/11/19

b. Full Closure of NE 8th St. Between NE 1st and NE 2nd Ave due to Gas line installation.

    • Time: 8AM to 4PM
    • Duration  05/15/2019 to 05/17/2019

c. Partial Lane Closure (2 Traffic Lanes) on NE 2nd Ave between NE 9th ST and NE 10th ST

    • Excavation of landscape area behind curb
    • Time: 8AM to 4PM
    • Duration 05/08/2019 to 05/15/2019

4. MWC Luma

a. Demolition of Unforeseen Concrete Foundations
b. Grading Site to 9.00NGVD
c. Haul Off of Site Soil and Demolition Soil
d. Test Pile and Production Program (will extend to after 5 PM)
e. Drilling of temporary and Permanent Drainage Wells

NOTE: All Concrete pours anticipated to start at 1am.