Construction Update Week of May 21, 2018

For your information, the following is a list of “Key” activities that will be occurring around the site over the next couple of weeks.

1. Paramount:

a. Concrete pours continue; currently pouring levels 50 and up.
b. Window installation continues to follow concrete.
c. Wall layout, framing, and interior finishes are ongoing.
d. Elevator bracket and rails installation ongoing.
e. Elevator frames from 2nd thru 40th floors.

2. 7th Street Apartments Project: On Wednesdays the pours are taking place from 8PM to 11PM.

a. Pool Deck – interstitial deck planter walls and framing of pool continues.
b. Window installation continues on levels 42 through 43.
c. Interior framing and MEP rough-ins continue in apartment units.
d. CMU installation in Garage continues.
e. Location: Partial lane closure on N. Miami Ave. between NW 7th St. and 8th St. by FPL.

• Duration: 03/29/18 thru 06/29/18
• Time of closure: 9PM to 8AM.

3. Block D East:

a. Continue MEP installation throughout the building.
b. Miscellaneous metal installation.
c. Formwork, rebar, pour concrete at Level 2 Mechanical opening.
d. Masonry installation Level 1 and Level 4 EMR’s.
e. Gate Precast surveying.

4. Site Work:

a. Drainage installation along NE 8th St. between 1st and 2nd Ave. (South side)

• Full Street Closure dates: 04/11/18 – 06/01/18
• Time of Closure: 8:30Am – 4:30PM.

b. Road reconstruction NE 10th St. between 1st and 2nd Ave.

• Full Street Closure Dates: 05/21/18 – 06/11/18

NOTE: All Concrete pours anticipated to start at 1am.