1. Paramount:

a. Concrete pours on continue on level 7.
b. Concrete Pour Level 8 to Start
c. MEP rough in 3rd floor.
d. Masonry block walls to start.
e. 2 day Full Street Closure on May 27th and 28th – to jump up the crane – NE 8th Street Between NE 1st Ave. and NE 2nd Ave.
f. Digging parking garage at north side and installing grade beams.
g. Buck Hoist to be installed.

2. 7th Street Apartment Project:

a. Concrete pour on level 12 and 13.
b. Concrete pour on Level 9 core.
c. Drywall Framing on Level 2 and 3.
d. Jumping up the Tower Crane.
e. Jumping up the Buck Hoist from Level 5 to Level 10.
f. Laying block in Garage and on Level 6 of tower.
g. Windows delivery.

3. Retail at Miami Worldcenter:

a. Placing concrete for foundations.
b. Begin to go vertical with columns and deck forming.
c. Ongoing rebar deliveries.

NOTE: All Concrete pours anticipated to start at 1am.