Construction Update Week of March 5, 2018

For your information, the following is a list of “Key” activities that will be occurring around the site over the next couple of weeks.

1. Paramount:

a. Concrete pours continue; currently pouring levels 43 and up.
b. Window installation continues to follow concrete.
c. Wall layout, framing, and interior finishes are ongoing.
d. Full closure of NE 10th St. between NE 1st and 2nd Ave. for a Sewer connection – Continues.

• Closure Dates: 02/27/18 to 03/16/18.
• Closure time: 7AM to 4PM.

2. 7th Street Apartments Project:

a. Concrete pour on the parapet wall on roof and Parking Garage.
b. Pool Deck – interstitial deck planter walls and framing of pool begins.
c. CMU Installation on perimeter continues – levels 41-43.
d. Window installation continues to follow CMU.
e. Interior framing and MEP rough-ins continue in apartment units.

3. Block D East:

a. Forming roof top pools.
b. Slab on grade continues.
c. Continue MEP installation throughout the building and underground.
d. Chiller will be hoisted to the roof for installation.

4. Site Work:

a. Drainage installation along NE 1st Ave. between 8th and 6th street (East/West side).

• Parking lane and side walk closure on NE 1st Ave.
• Closure Duration: 02/26/18 – 03/26/18 8PM – 5AM.

b. Drainage installation along NE 1st Ave between RR Tracks and NE 8th ST – West Side.

c. Full closure of NE 1st Ave. between NE 6th and 8th St. by FPL

    • Closure Dates: 03/11/18 to 03/15/18
    • Closure time: Night time closure only.

NOTE: All Concrete pours anticipated to start at 1am.