Construction Update Week of March 19, 2018

For your information, the following is a list of “Key” activities that will be occurring around the site over the next couple of weeks.

1. Paramount:

a. Concrete pours continue; currently pouring levels 46 and up.
b. Window installation continues to follow concrete.
c. Wall layout, framing, and interior finishes are ongoing.
d. Full closure of NE 10th St. between NE 1st and 2nd Ave. for a Sewer connection – Continues.

• Closure Dates: 03/19/18 to 04/16/18.
• Closure time: 8 PM to 5AM.

e. Full closure of NE 1st Ave. between NE 8th and 9th St.

• Closure Dates: 03/11/18 to 04/15/18.
• Closure time: Night time closure only.

f. Partial lane closure on N. Miami Ave. between NW 6th St. and 8th st. by FPL.

• Closure Dates: 03/29/18 thru 06/29/18
• Closure time: 9PM to 8AM.

2. 7th Street Apartments Project: On Wednesdays the pours are taking place from 8PM to 11PM.

a. Concrete pour on the parapet wall on roof and Parking Garage.
b. Pool Deck – interstitial deck planter walls and framing of pool begins.
c. CMU Installation on perimeter continues.
d. Window installation continues to follow CMU.
e. Interior framing and MEP rough-ins continue in apartment units.

3. Block D East:

a. Forming roof top pools.
b. Slab on grade continues.
c. Continue MEP installation throughout the building and underground.
d. Chiller will be hoisted to the roof for installation.

4. Site Work:

a. Drainage installation along NE 1st Ave. between 8th and 6th street (East/West side)

• Parking lane and side walk closure on NE 1st Ave.
• Closure Duration: 02/26/18 – 03/30/18 8PM – 5AM.

NOTE: All Concrete pours anticipated to start at 1am.