Construction Update Week of March 18, 2019

For your information, the following is a list of “Key” activities that will be occurring around the site over the next couple of weeks.

1. Paramount:

a. Partial Lane Closure on NE 10th St. between NE 1st Ave and NE 2nd Ave.:

• Duration: 03/08/19 – 03/22/19
• Time: from 7:30 AM to 6:30 PM

b. Full road Closure on NE 10th St. between NE 1st Ave and NE 2nd Ave.:

• Duration: 03/25/19 – 03/25/19
• Time: from 7:00 AM to 5:00 PM

c. Building Enclosure at Podium continues
d. Interior finishes continue
e. Amenity deck continues

2. Block D East:

a. Elevators Installation is ongoing and nearing completion.
b. Installation of the facade Façade panels on the east elevation is ongoing.
c. Installation of the steel supporting members for the louvers continues.
d. Off-site utilities installation along 2nd Avenue continues.

3. Site Work:

a. Partial Closure on NE 8th St. Between NE 1st and NE 2nd Ave due to Gas line installation.

• Time: 7AM to 4PM
• Duration 02/25/2019 to 03/29/2019

b. Full Closure on NE 1st Ave from NE 8th to 10th St (West Half Road Reconstruction). Full Closure for NE 8th St from NE 1st to N Miami (Access to NAP remains open from N Miami Ave.)

• Time: 24 HRS
• Duration: 03/11/19 – 04/05/19

c. Partial Lane Closure (2 Traffic Lanes) on NE 2nd Ave between NE 8th ST and NE 9th ST

• Demolition / Water and Sewer / Electrical Mains/ Irrigation Mains
• Time: 8AM to 4PM • Duration 03/11/2019 to 04/01/2019

4. MWC Luma

a. Demolition of Unforeseen Concrete Foundations
b. Grading Site to 9.00NGVD
c. Haul Off of Site Soil and Demolition Soils

NOTE: All Concrete pours anticipated to start at 1am.

903749

903748

903747

903746

 

 

 



Contact Us