For your information, the following is a list of “Key” activities that will be occurring around the site over the next couple of weeks.

  1. Paramount:
    • Partial Lane Closure on NE 10th St. between NE 1st Ave and NE 2nd Ave.:
      • Duration: 03/08/19 – 03/22/19
      • Time: from 7:30 AM to 6:30 PM
    • Full road Closure on NE 10th St. between NE 1st Ave and NE 2nd Ave.:
      • Duration: 03/25/19 – 03/25/19
      • Time: from 7:00 AM to 5:00 PM
    • Building Enclosure at Podium continues
    • Interior finishes continue
    • Amenity deck continues
  2. Block D East:
    • Elevators Installation is ongoing and nearing completion.
    • Installation of the facade Façade panels on the east elevation is ongoing.
    • Installation of the steel supporting members for the louvers continues.
    • Off-site utilities installation along 2nd Avenue continues.
  3. Site Work:
    • Partial Closure on NE 8th St. Between NE 1st and NE 2nd Ave due to Gas line installation.
      • Time: 7AM to 4PM
      • Duration 02/25/2019 to 03/29/2019
    • Full Closure on NE 1st Ave from NE 8th to 10th St (West Half Road Reconstruction). Full Closure for NE 8th St from NE 1st to N Miami (Access to NAP remains open from N Miami Ave.)
      • Time: 24 HRS
      • Duration: 03/11/19 – 04/05/19
    • Partial Lane Closure (2 Traffic Lanes) on NE 2nd Ave between NE 8th ST and NE 9th ST
      • Demolition / Water and Sewer / Electrical Mains/ Irrigation Mains
      • Time: 8AM to 4PM • Duration 03/11/2019 to 04/01/2019
  4. MWC Luma
    • Demolition of Unforeseen Concrete Foundations
    • Grading Site to 9.00NGVD
    • Haul Off of Site Soil and Demolition Soils

NOTE: All Concrete pours anticipated to start at 1am.