Construction Update Week of June 4, 2018

For your information, the following is a list of “Key” activities that will be occurring around the site over the next couple of weeks.

1. Paramount:

a. Concrete pours continue; currently pouring levels 51 and up.
b. Window installation continues to follow concrete.
c. Wall layout, framing, and interior finishes are ongoing.
d. Elevator bracket and rails installation ongoing.
e. Elevator frames from 2nd thru 40th floors.

2. 7th Street Apartments Project: On Wednesdays the pours are taking place from 8PM to 11PM.

a. Pool Deck amenities building concrete placement continues.
b. Window installation continues on level 43.
c. Interior framing and MEP rough-ins continue in apartment units and corridors.
d. CMU installation in Garage continues.
e. Tower Crane Removal.
f. Weekend deliveries.
g. Location: Partial lane closure on N. Miami Ave. between NW 7th St. and 8th St. by FPL.

• Duration: 03/29/18 thru 06/29/18
• Time of closure: 9PM to 8AM.

3. Block D East:

a. Continue MEP installation throughout the building.
b. Miscellaneous metal installation.
c. Formwork, rebar, pour concrete at Level 2 Mechanical opening.
d. Masonry installation Level 1 and Levels 6 & 8 EMR’s.
e. Barrier cable installation.
f. Elevators Installation.

4. Site Work:

a. Drainage installation along NE 8th St. between 1st and 2nd Ave. (South side).

• Full Street Closure dates: 04/11/18 – 06/11/18.
• Time of Closure: 8:30Am – 4:30PM.

b. Road reconstruction NE 10th St. between 1st and 2nd Ave.

• Full Street Closure Dates: 05/21/18 – 06/18/18.

c. Road demolition NE 7th St. between NE 2nd and NE 1st Ave.

• Currently vacated street.

NOTE: All Concrete pours anticipated to start at 1am.