For your information, the following is a list of “Key” activities that will be occurring around the site over the next couple of weeks.

  1. Paramount:

    • Partial Lane Closure on NE 10th St. between NE 1st Ave and NE 2nd Ave.:
      • Duration: 05/01/19 – 06/30/19
      • Time: from 7:30 AM to 6:30 PM
    • Partial Lane closure; most eastern lanes on 1st Ave. between NE 8th and NE 10th Street
      • Duration: 05/01/19 – 07/31/19
      • Time: 24 Hours
    • Building Enclosure at Podium continues
    • Interior finishes continue
    • Amenity deck continues
  2. Block D East:
    • Amenity deck continues
    • Installation of the metal fins started on the north elevation
    • Off-site utilities installation along 2nd Avenue continues
    • Partial Lane Closure (1 Traffic Lanes) on NE 2nd Ave between NE 8th ST and NE 10th ST
      • Installation of Pavers
      • Time: 8AM to 4PM
      • Duration 06/24/19 – 06/28/19
  3. Site Work:
    • 2 Lane closure on N Miami Ave. between 8th St. and R/R tracks.
      • Excavation and installation of drainage
      • Time: 8AM to 4PM
      • Duration: 05/03/19 – 05/11/19
    • Partial Lane and Side walk closure on N Miami Ave.
      • Drainage and Electrical Work
      • Time: 8AM to 4PM
      • Duration: 06/24/19 -06/30/19
  4. MWC Luma
    • Installing tower production piles
    • Installing tower sheet piles
    • Start installing garage production piles
    • Installing temp power
    • Installing permanent wells

NOTE: All Concrete pours anticipated to start at 1am.