Construction Update Week of July 30, 2017

For your information, the following is a list of “Key” activities that will be occurring around the site over the next couple of weeks.

1. Paramount:

a. Concrete pour level 16: floor, vertical walls and columns.
b. Window unload and install on levels 9 and 10.
c. Garage footers and vertical pours.
d. MEP material delivery.

2. 7th Street Apartments Project:

a. Window Install from Levels 9 and up.
b. Concrete pour on Level 21.
c. Core slab pour on level 18.
d. Slab on Grade Pour.
e. Buck hoist jump from level 15 to level 18.

3. Retail at Miami Worldcenter:

a. Concrete pour level 4.
b. Form work continuing on level 5.
c. Striping level 3.
d. Crane set up.

NOTE: All Concrete pours anticipated to start at 1am.