Construction Update Week of July 16, 2018

For your information, the following is a list of “Key” activities that will be occurring around the site over the next couple of weeks.

1. Paramount:

a. Concrete pours continue; currently pouring levels 56 and up.
b. Window installation continues to follow concrete.
c. Wall layout, framing, and interior finishes are ongoing.
d. Elevator bracket and rails installation ongoing.
e. Elevator frames from 2nd thru 45th floors.
f. NE 1st Ave. Night full road closure.

• Location: 1st Ave between NE 8th and 10th St. • Dates: 07/16/18 – 07/20/18

2. 7th Street Apartments Project:

a. Pool Deck amenities building concrete placement continues.
b. Window installation continues on level 43.
c. Interior framing and MEP rough-ins continue in apartment units and corridors.
d. CMU installation in Garage continues.
e. Material deliveries on weekends.

3. Block D East:

a. Continue MEP installation throughout the building.
b. Miscellaneous metal installation.
c. Formwork, rebar, pour concrete at Level 2 Mechanical opening.
d. Masonry installation continues throughout the building.
e. Barrier cable installation.
f. Elevators Installation.
g. NE 2nd Ave. full road closure between 8th and 9th St. (See attached drawing).

• Duration: 07/27/18 – 07/30/18 • Time of Closure: 24 hours

4. Site Work:

a. Road reconstruction NE 10th St. between 1st and 2nd Ave.

• Full Street Closure Dates: 07/12/18 – 07/20/18.

b. Road demolition NE 7th St. between NE 2nd and NE 1st Ave.

• Currently vacated street.

c. Drainage installation for Paramount Tower on NE 1st Ave. between NE 8th and 10th St.

• Full Street Closure dates: 07/16/18 – 07/25/18 • Night time closure only

NOTE: All Concrete pours anticipated to start at 1am. 870872   870877   870876   870873     870875   map