Construction Update Week of July 16, 2017

For your information, the following is a list of “Key” activities that will be occurring around the site over the next couple of weeks.

1. Paramount:

a. Levels 14th and 15th floor slab pour.
b. Back fill at parking garage continues.
c. Rough MEP installation on levels 7th and 8th.

2. 7th Street Apartments Project:

a. FRP L 15, Pour 2 – Elevator Core.
b. Concrete pour Level 19 and 20.
c. Install SGD level 2.
d. Framing fire walls levels 5, 6 and 7.
e. Buck Hoist and Tower Crane Jump.

3. Retail at Miami Worldcenter:

a. Concrete Pour on level 3.
b. Forming removal on level 2.
c. Forming on Level 4 Continues.

NOTE: All Concrete pours anticipated to start at 1am.