Construction Update Week of January 6, 2020

For your information, the following is a list of “Key” activities that will be occurring around the site over the next couple of weeks.

1. Paramount:

a. Villas window install continues

b. Villa area Amenity deck construction continues

2. Work by Others – Allegiance Crane for the NAP (Not by CoastalTishman)

a. Two lane closure on NE 1 Ave. between NE 8th and NE 9th Street

• Dates: 02/10/20, 02/17/20 and 02/24/20

• Time: 10:00 PM to 06:00 AM

3. D East

a. Sidewalk partially closed on NE 2nd Ave. (West Side)

• Dates: 01/18/20 to 01/21/20

• Time: 08:00AM to 05:00PM

4. MWC Luma

a. Tower

• Forming and pouring verticals – daytime

• Forming Slabs – daytime

• Pouring Slabs

• FRP Verticals at Garage

• All Concrete Pours start at 04:00 AM

948630

948631

948633

948640

948641