Construction Update Week of January 28, 2019

For your information, the following is a list of “Key” activities that will be occurring around the site over the next couple of weeks.

1. Paramount:

a. Amenity deck waterproofing and installation of swimming pools continue.
b. Window installation continues.
c. Elevator bracket and rail installation is ongoing.
d. Interior Finishes continue.
e. North and South Hoist removal will commence.
f. Partial Lane Closure on NE 10th St. between NE 1st Ave and NE 2nd Ave.:

• Duration: 01/20/19 – 02/20/19
• Time: from 7:30 AM to 6:30 PM

2. 7th Street Apartments Project:

a. Interior Punchout continues.
b. Façade panels install continues.
c. Final Painting
d. Completion of Dog walk in garage area.

3. Block D East:

a. Elevators Installation is ongoing.
b. Doors and door frames installations continue.
c. Installation Façade Metal panels and sub framing on the south elevation.
d. Installation of the steel supporting members for the louvers.
e. Installation of the temporary walls continues.
f. Off-site utilities installation along 8th St. continues.

 4. Site Work:

a. Partial Closure on NE 8th St. Between NE 1st and NE 2nd Ave due to Gas line installation.

• Time: 8AM to 4PM
• Duration 02/11/2019 to 02/15/2019

          b. Partial Closure on NE 1st Ave. Between NE 1st from NE 8th to 10th St (East Half Road Reconstruction). Traffic will be reduced to 1 lane.

• Time: 24 HRS
• Duration: 02/18/19 – 03/29/19

5. Site Utilities

a. Road Reconstruction to begin at NIGHT along NE 1st Ave from NE 8th ST to NE 10th ST (East Half of Road)

• Monday 02.18.19 to Friday 03.08.19
• Traffic along NE 1st Ave will be reduced to One Lane

NOTE: All Concrete pours anticipated to start at 1am.