For your information, the following is a list of “Key” activities that will be occurring around the site over the next couple of weeks.

  1. Paramount:
    • Amenity deck waterproofing and installation of swimming pools continue.
    • Window installation continues.
    • Elevator bracket and rail installation is ongoing.
    • Interior Finishes continue.
    • North and South Hoist removal will commence.
    • Partial Lane Closure on NE 10th St. between NE 1st Ave and NE 2nd Ave.:
      • Duration: 01/20/19 – 02/20/19
      • Time: from 7:30 AM to 6:30 PM
  2. 7th Street Apartments Project:
    • Interior Punchout continues.
    • Façade panels install continues.
    • Final Painting
    • Completion of Dog walk in garage area.
  3. Block D East:
    • Elevators Installation is ongoing.
    • Doors and door frames installations continue.
    • Installation Façade Metal panels and sub framing on the south elevation.
    • Installation of the steel supporting members for the louvers.
    • Installation of the temporary walls continues.
    • Off-site utilities installation along 8th St. continues.
  4. Site Work:
    • Partial Closure on NE 8th St. Between NE 1st and NE 2nd Ave due to Gas line installation.
      • Time: 8AM to 4PM
      • Duration 02/11/2019 to 02/15/2019
    • Partial Closure on NE 1st Ave. Between NE 1st from NE 8th to 10th St (East Half Road Reconstruction). Traffic will be reduced to 1 lane.
      • Time: 24 HRS
      • Duration: 02/18/19 – 03/29/19
  5. Site Utilities
    • Road Reconstruction to begin at NIGHT along NE 1st Ave from NE 8th ST to NE 10th ST (East Half of Road)
      • Monday 02.18.19 to Friday 03.08.19
      • Traffic along NE 1st Ave will be reduced to One Lane

NOTE: All Concrete pours anticipated to start at 1am.