Construction Update Week of January 14, 2019

For your information, the following is a list of “Key” activities that will be occurring around the site over the next couple of weeks.

1. Paramount:

a. Concrete pours at the amenity deck and pools is in progress.
b. Window installation continues.
c. Wall layout, framing, and interior finishes are ongoing.
d. Elevator bracket and rails installation ongoing.
e. North and South Hoist take down 12/19/18 and 01/20/19.
f. NE 10th St. full Road closure:

• Duration: 01/02/19 -01/30/19
• Time: from 7:30 AM to 6:30 PM

2. 7th Street Apartments Project:

a. Retail Window installation continues.
b. Interior Punchout continues.
c. Material deliveries on weekends.
d. Façade panels install continues.

3. Block D East:

a. Elevators Installation is ongoing.
b. Stucco work continues.
c. Doors and door frames installations continue.
d. Installation Façade Metal panels and sub framing on the north elevation.
e. Installation of the steel supporting members for the louvers.
f. Installation of the temporary walls started.

4. Site Work:

a. Full Road closure on NE 1st Ave between R/R and 8th St.

• Duration 01/14/19 to 01 /16/19

b. Daily Road Closure as needed on NE 8th St. Between NE 1st and NE 2nd Ave

• Duration 01/14/2019 to 01/25/2019

NOTE: All Concrete pours anticipated to start at 1am.