Construction Update Week of February 24, 2019

For your information, the following is a list of “Key” activities that will be occurring around the site over the next couple of weeks.

1. Paramount:

a. Partial Lane Closure on NE 10th St. between NE 1st Ave and NE 2nd Ave.:

• Duration: 01/20/19 – 03/08/19
• Time: from 7:30 AM to 6:30 PM

2. Block D East:

a. Elevators Installation is ongoing.
b. Installation Façade Metal panels on the east elevation is ongoing.
c. Installation of the steel supporting members for the louvers continues.
d. Off-site utilities installation along 2nd Avenue continues.

3. Site Work:

a. Partial Closure on NE 8th St. Between NE 1st and NE 2nd Ave due to Gas line installation.

• Time: 7AM to 4PM
• Duration 02/25/2019 to 03/15/2019

b. Partial Closure on NE 1st Ave. Between NE 1st from NE 8th to 10th St (East Half Road Reconstruction). Traffic will be reduced to 1 lane.

• Time: 24 HRS
• Duration: 02/18/19 – 03/29/19

c. Partial Lane Closure on NE 2nd Ave between NE 8th ST and NE 9th ST

• Demolition / Water and Sewer / Electrical Mains/ Irrigation Mains
• Time: 8AM to 4PM
• Duration 02/25/2019 to 03/08/2019

NOTE: All Concrete pours anticipated to start at 1am.

899833

 

 

 

899834

 

 

 

895450

 

 

Capture1

 

 

Capture



Contact Us